KURICHHU HYDROPOWER PLANT
Background

The Kurichhu Hydropower Plant is located at Gyelpozhing, Mongar on the Kurichhu River in Eastern Bhutan. It is a run-of-river scheme, with a dam of height 55m (from its deepest foundation), crest length of 285 m and a surface power house located at the toe of the dam. The Project has an installed capacity of 60 MW consisting of four units of 15 MW each and a mean annual energy generation capacity of 400 million units (MU). The Kaplan turbine operates with a net head of 32 m and discharge of 53m3/sec per unit. A unique feature of the project is the fish ladder for migration of fish.
The Kurichhu Project Authority was established to control and monitor the construction work, and to arrange funds for the construction. The Authority entered into an agreement with the National Hydroelectric Power Corporation Ltd., (NHPC) a Government of India agency, for the turnkey execution of the project. The Authority appointed Water and Power Consultancy Services (WAPCOS) as review Consultants. The construction activities started in 1995 with the diversion tunnel works.
NHPC separately entered into a contract agreements with M/s. Asian Techs Ltd. for the construction of the diversion tunnel, with M/s. Hindustan Construction Company for the construction of dam, with M/s. Gammon India Ltd. for the construction of power house, with M/s. Bharat Heavy Electricals Ltd. for the supply and erection of electro-mechanical equipment, and with M/s. Om Metals and Minerals Limited for the supply and erection of hydro-mechanical equipment, and with M/s. Prem Power Construction Ltd. for the construction of 132 kV transmission lines. A host of other smaller Indian and Bhutanese firms also participated in the construction of the Project.
The first 15 MW machine was spun on 13th April 2001. This first unit was synchronized to the Indian North Eastern grid on 13th August 2001, followed by the second unit on 15th August 2001, and the third unit on 27th September 2001. Commercial operation started from 1st November 2001. The fourth Unit was commissioned on 31st May 2002.
The Kurichhu Hydropower Plant was formally inaugurated by HRH Trongsa Penlop Jigme Khesar Namgyel Wangchuck and H.E Shri Sudhir Vyas, Ambassador of India to Bhutan on 26th April 2006.
Project Finance
In February 1994, the Government of India and the Royal Government of Bhutan entered into Agreement to construct the project wherein the Government of India agreed to finance the Project in the ratio of 60% grant and 40% loan repayable over a period of 12 years at a simple interest rate of 10.75%. The final cost of the Project on completion, including 68 km of 132 kV transmission line from Gyelpozhing to Nanglam, was Nu. 5,600 million excluding interest accrued during construction. The Royal Government of Bhutan further funded Nu. 40 million towards acquisition of land, providing communication network, and other infrastructure not covered under the scope of the Project.
The repayment of loan component amounting to Nu. 2240 million to the Government of India started in July 2004, the interest accrued during construction amounted to Nu.1,035.529 million. So far Nu. 746.667 million of the loan amount was paid and a total of Nu.1.553 billion was paid including principal and interest at the rate of 10.75% per annum.
The transmission system of KHP was handed over to BPCL on December 31, 2003 along with all the assets, inventories, and associated manpower with a total assets value Nu. 641,494,889.26.
Salient Features of Kurichhu Hydropower Plant (4 x 15 MW)
Country | : Bhutan |
District | : Mongar |
River | : Kurichhu |
Dam & Powerhouse Site | : Gyelpozhing |
Longitude | : 91012’ E |
Latitude | : 27013’ N |
Dam/Reservoir

Type | Concrete gravity |
Height above the deepest Foundation | : 55 m |
Length of Dam at top | : 285 m |
Dam top elevation | : 535 m.a.s.l |
Full Reservoir Level (FRL) | : 531 m.a.s.l |
Maximum Reservoir Level | : 534 m.a.s.l |
Minimum Draw Down Level | : 526 m.a.s.l |
Gross poundage upto FRL | : 15.70 M m³ |
Dead pondage upto MDDL | : 11.25 M m3 |
Spillway opening type/Nos. | : Orifice/5 |
Number of Intake Gates | : 2 |
Number of Fish Pass Gates | : 2 |
Hydrology
Catchment Area Snow fed catchment | : 9135 km2 |
Above EL 3500 m Rain fed catchment | : 6385 km2 |
Below EL 3500 m | : 2750 km2 |
Standard Project Flood | : 9300 m3/sec |
Probable Maximum Flood | : 12200 m3/sec |
Average Annual Run Off | : 9179 M m3 |
Average Monsoon Run Off (June to Oct.) | : 6345 M m3 |
Average Non-Monsoon Run Off (Nov. to May) | : 2834 M m3 |
Spillway
Type | : Orifice |
Crest Elevation | : 506 m |
Type of Gate | : Radial |
Number of Gates | : 5 |
Size of Gates | : 10.5 x 14.5 (m) |
Energy dissipation | : Stilling basin |
Cistern Level | : El. 485 m |
Length of Stilling Basin | : 104 m |
Fish Ladder
Location | : Right bank Non-overflow block |
Type | : Pool Pass with Submerged orifice |
Length of Pool | : 103 m |
Depth of each pool | : 1.5 m |
Width of pool | : 1.5 m |
Power House
Type | : Surface |
Location | : Dam toe |
Installed capacity | : 4x15 MW |
Type of Turbine | : Vertical Shaft Kaplan |
No. of Turbine Blades | : 6 |
Type of Generator | : Semi Umbrella |
Net Head | : 32 m |
Discharge per machine | : 53 m3/Sec |
Rated Speed | : 250 rpm |
Power Intake and Penstock
Location | : Non-Overflow Block on Left Bank |
Type | : Dam body |
No. of Intake | : 2 |
Dia. of Intake | : 4.75 m |
Dia. of penstock | : 4 m |
Tail Race System
Type | : Open Channel |
Length | : 40.50 m |
Weir Level | : 494 m |
Switch Yard
Type | : Open Door |
Transmission Voltage | : 132 kV |
No. of Feeders | : 2 |
Generator Transformer Rating/Nos. | : 20 MVA/4 |
Transmission Line
No. of Circuit | : Single |
Length | : 198 km |
Voltage | : 132 kV |
Shunt Reactor
No. of Reactors | : 2 |
Capacity of each reactor | : 5 MVAR |
Operational and Financial Performance
During the peak power generation season, over 60% of the power generated from the Plant is being exported to India. The Kurichhu Hydropower Plant is providing power supply to eight Dzongkhags in eastern and central Bhutan. The drastic increase in the domestic consumption since February 2007 was mainly due to the commissioning of Ferro-Silicon factory at Motanga/Rabtenling Industrial estate at Samdrupjongkhar. The performance of KHP in generation, export to India, and sale to BPC for the last three years is shown in figure below :
KHP is still faced with frequent outages of single transmission line which restricts the full generation during the peak season. Over the years the performance of KHP had improved significantly while in 2008, KHP had achieved highest generation so far. With ever expanding rural electrification and with urban and industrial growth the domestic consumption is increasing rapidly, resulting in revenue decreases.
It may be noted that the most recent revision of KHP export power tariff was negotiated between the two governments of India and Bhutan on 12/12/2007 where in the export power tariff was revised from Rs. 1.75 per Unit to Rs. 1.80 per Unit with effect from 1st January 2008. It was also agreed that henceforth the KHP export tariff will be pegged to THP export tariff and whenever there is a revision in the power tariff of the later, the KHP export tariff will also automatically stand revised.
(Nu. per kWh) | Nov. 1, 2001-Sep . 30, 2002 | Aug. 1, 2002-Jan. 31, 2007 | Feb. 1-Jun. 2007 | July 1- Dec.31, 2007 | Jan 2008- |
Export | 1.75 | 1.75 | 1.75 | 1.75 | 1.80 |
Import | 1.55 | 1.75 | 1.75 | 1.75 | 1.80 |
Sale to BPC | 0.30 | 0.30 | 0.30 | 0.30 | 0.30 |
Sale to Montanga Industrial Estate | - | - | 1.20 | 1.29 | 1.29 |
Demand Charge (per kW) per month | - | - | 54 | 65 | 65 |
Manpower
Total Number of STAFF | 180 |
Bhutanese Employees | 178 |
Non-Bhutanese Employees | 2 |
Male Employees | 159 |
Female Employees | 21 |
Regular Employees | 179 |
Contract Employees | 1 |
CHP Grade | RCSC Grade | Proposed Grade | Level | Masters | Bachelors | Diploma | Level 1 | Level 2 |
A1 | 2 | E1 | Executive | | | | | |
A | 3 | E2 | Executive | | | | | |
B | 4 | E3 | Executive | | | 1 | | |
C | 5 | M1 | Managerial | | | | | |
D | 6 | M2 | Managerial | 2 | 3 | 1 | | |
E | 7 | M3 | Managerial | 1 | 4 | | | |
F | 8 | S1 | Supervisory | | 2 | 13 | | |
G | 9 | S2 | Supervisory | | | 9 | | |
KHP Organogram
