The 1,020 MW Punatsangchhu-II Hydroelectric Project (PHPA-II) successfully synchronised two units of 170 MW each with the national grid on December 17. Following the synchronisation, mandatory Grid Code tests are underway, with completion expected in a few days. Once the tests are completed, the Bhutanese System Operator will issue the Commercial Operation Date certificate. Until…