Business scope : Develops all small hydropower projects in Bhutan
Incorporation   : December 16, 2021
Shareholder      : DGPC (100%)

Jigmeling, Sarpang
email: info.dhye@dhye.bt
For more details, visit https://dhye.drukgreen.bt

PHASE I PROJECTS

Burgangchhu HPP

Location                : Nangkhor, Zhemgang
Capacity               : 54 MW
Project scheme    : Run-of-the-river
Design energy      : 260.51 MU
Project cost          : Nu. 3,565.25 million
Project schedule  : 2022 – 2025

Yungichhu HPP

Location                 : Medtsho, Lhuentse
Capacity                : 32 MW
Project scheme     : Run-of-the-river
Design energy       : 157.6 MU
Project cost           : Nu. 3,660 million
Project schedule  : 2022 – 2025

Suchhu HPP

Location                : Sangbaykha, Haa
Capacity               : 18 MW
Project scheme    : Run-of-the-river
Design energy      : 76.57 MU
Project cost          : Nu. 2,095 million
Project schedule  : 2022 – 2024

PHASE II PROJECTS

Jomori HPP

Location               : Jomotshangkha, SJ
Capacity              : 90 MW
Project scheme   : Run-of-the-river
Design energy     : 367 MU
Project cost         : Nu. 8,509 million
Project schedule : 2023 – 2028

Druk Bindu I&II HPP

Location               : Tendu, Samtse
Capacity              : 26 MW
Project scheme   : Run-of-the-river
Design energy     : 109.82 MU
Project cost         : Nu. 2,654.49 million
Project schedule : 2023 – 2026

Gamri I HPP

Location               : Sakteng, Trashigang
Capacity              : 54 MW
Project scheme   : Run-of-the-river
Design energy     : 228 MU
Project cost         : Nu. 5,876.42 million
Project schedule : 2023 – 2027

Begana Integrated HPP

Location               : Begana, Thimphu
Capacity              : 25 MW
Project scheme   : Run-of-the-river
Design energy     : 104 MU
Project cost         : Nu. 2,694.48 million
Project schedule : 2023 – 2026