Installed capacity : 4 X 150 MW
Design energy : 2,568.88 MU
Project cost : Nu. 38.69 billion
Incorporation : June 12, 2015
Project schedule : September 2015 – 2025
Shareholders : DGPC (50%), SJVN (50%)
Trashiyangtse
Tel: +975 8 781139/44
For more details, visit www.khepbhutan.com